HUNTER INTERNATIONAL SPORTS CENTRE TRUST
Artists Impression of Hunter International Sports Centre
About Hunter ISC Trust
About Hunter ISC Trust
The Trustees
The Master Plan
EA Stadium Development
Latest News
Why a new stadium?
Construction Stages
Stadium Capacity
Stadium Images
Stadium & Sports Park Usage
Economic Boost for the Hunter
History of the Stadium
Sports Facility Zone
HISC Facilities
Newcastle Harness Racing Club
Newcastle Hockey Centre
Other Facilities
Contact Us
Links
HISC EnergyAustralia Stadium Redevelopment   Hunter International Sports Centre Trust (logo) HISC

Stadium Images

Below are design plans for the redevelopment of EnergyAustralia Stadium plus photographs of the redevelopment.

bullet Eastern Grandstand Designs
 

Eastern Concourse

 

Corporate Box Level

 

Upper Stand 1

 

Upper Stand 2

 

Cross-section of Eastern Grandstand

bullet Stadium Redevelopment
 

The Eastern Concourse before the start of demolition (September 2003)

 

The first stage of the redevelopment was stripping out and dismantling the corporate boxes (October 2003)

 

Demolition on the corporate boxes continues (October 2003)

 

The bucket seats from the Eastern Concourse have been relocated to the Northern and Southern Concourses (October 2003)

 

With the corporate boxes removed, it was time for the old scoreboard to be removed (October 2003)

 

The old scoreboard being removed (October 2003)

 

Demolition now completed (November 2003)

 

Demolition now completed (November 2003)

 

Drilling rig testing the foundations on the Eastern Concourse (November 2003)

  Drilling rig testing the foundations on the Eastern Concourse (November 2003)
  Excavation work continues on the Eastern Concourse (January 2004)
  Preliminary concreting and form work at the northern end of the Eastern Concourse (February 2004)
  Second tier of concreting (February 2004)
  Second tier of concreting continued (February 2004)
  While the concrete tiering continued through to the southern end of the concourse, work started on the installation of the seating brackets at the northern end (February 2004)
  Installation of the seating brackets at the northern end (March 2004)
  With the seating brackets installed at the northern end, work started on the final tier of concrete (March 2004)
  Installation of the new corporate boxes on the Northern Hill (March 2004)
  The first of the new corporate boxes on the Northern Hill (March 2004)
  Concrete pouring continuing on the final tier (March 2004)
  Concreting nears completion (April 2004)
  Installation of seating starts (April 2004)
  Installation of the seats was finished in time for the first Knights home game on April 18
  Installation of the seats was finished in time for the first Knights home game on April 18
  The new Eastern Concourse (May 2004)
  The new Eastern Concourse (May 2004)
  The new Eastern Concourse (May 2004)
  Work on the upper deck started in May 2004
  Construction crews working on the upper deck amenities (August 2004)
  Lift well access on the upper deck (August 2004)
  Scaffolding in place for the concrete pour of the southern section of the corporate facilities (August 2004)
  The centre section of the corporate level (August 2004)
  Installation of the upper deck plats (September 2004)
  Installation of the upper deck plats (September 2004)
  Installation of the upper deck plats (September 2004)
  The first of the roofing beams being put into place (September 2004)
  Temporary props were used to hold the roof structure in place (September 2004)
  Work continues on the upper deck (October 2004)
  More plats being installed (October 2004)
  Centre section of the upper deck nears completion (October 2004)
  Work also continues on the playing surface (October 2004)
  The concrete pour for the southern section of the corporate level (November 2004)
  Scaffolding moves into place for the corporate level concrete pour at the northern end (November 2004)
  Scaffolding starts for the upper deck concrete pour at the southern end (November 2004)
  More work is carried out in preparation for the new playing surface (November 2004)
  Roofing almost completed on the centre section (November 2004)
  Resurfacing process is completed (December 2004)
  Work starting on the southern section of the upper deck. In only a matter of days the new playing surface is showing tinges of green. (December 2004)
  Work continuing on the southern section of the upper deck. (December 2004)
  Concrete plats being lifted into place at the southern end of the upper deck (January 2005)
  Work continues on the southern section of the upper deck (January 2005)
  Work continues on the southern section of the upper deck (January 2005)
  Work continues on the southern section of the upper deck (January 2005)
  Work continues on the southern section of the upper deck (January 2005)
  Work continues on the southern section of the upper deck (January 2005)
  Work continues on the southern section of the upper deck (January 2005)
  Work continues on the southern section of the upper deck (January 2005)
  Installation of the roof on the southern section of the upper deck (January 2005)
  The new playing surface continues to green up (January 2005)
  Concrete pour on the northern section of the upper deck (January 2005)
  The first piece of the upper deck structure at the northern end of the grandstand (February 2005)
  Concrete plats almost finished in the northern section of the upper deck (February 2005)
  The final pieces of the grandstand roof being put into place (February 2005)
  With the roof now completed, construction crews work on removing the first of the temporary roof props (March 2005)
  Temporary roof prop being removed (March 2005)
  Temporary roof prop being removed (March 2005)
  The final prop is removed (March 2005)
  The upper deck of the new Eastern Grandstand will provide an unimpeded view of the playing field (March 2005)
  The new Eastern Grandstand was filled to capacity for the Knights first home game of the 2005 NRL season when they took on the New Zealand Warriors on Sunday, 17 April (photo courtesy www.knightsheadquarters.com)
  The new Eastern Grandstand (July 2005)
  The new Eastern Grandstand (July 2005)
  The Eastern Grandstands now dwarfs the existing Western Grandstand (July 2005)
  An aerial view of the Hunter ISC Trust Precinct (July 2005)
 
web site developers: CIBIS